Delhi: Third metro tunnel of Phase-III project at Janpath completed

Written By Unknown on Selasa, 23 April 2013 | 22.10

NEW DELHI: Delhi Metro on Tuesday completed the 1,516-metre tunnel on Mandi House-Janpath stretch of Phase-III project.

In the presence of Managing Director, DMRC Mangu Singh, the Tunnel Boring Machine (TBM) emerged at the Janpath metro station site after making a 1516 metre-long tunnel from Mandi House rotary on the up line, a DMRC official said.

The tunnel, with an internal diameter of 5.8 meters was excavated within 182 working days and passes beneath a lot of important central Delhi buildings like American Centre, Nepal Embassy, Fulbright House, Antriksh Bhawan, Scindia House, Electrical Sub Station, Janpath Market and Jeevan Prakash Building.

The TBM was lowered in the Mandi House shaft on September 25 last year and after assembly of the TBM below the ground the initial drive began on October 23 last.

The TBM broke through from the North West Shaft of the Janpath Metro station close to the Tibetan Market.


Anda sedang membaca artikel tentang

Delhi: Third metro tunnel of Phase-III project at Janpath completed

Dengan url

http://sehatputihgigiku.blogspot.com/2013/04/delhi-third-metro-tunnel-of-phase-iii.html

Anda boleh menyebar luaskannya atau mengcopy paste-nya

Delhi: Third metro tunnel of Phase-III project at Janpath completed

namun jangan lupa untuk meletakkan link

Delhi: Third metro tunnel of Phase-III project at Janpath completed

sebagai sumbernya

0 komentar:

Posting Komentar

techieblogger.com Techie Blogger Techie Blogger