Expressing concern over delay in the project, a bench headed by Chief Justice H L Dattu set a deadline of April to start construction. It directed the government to complete re-tendering of the project within two months.
Solicitor general Ranjit Kumar, appearing for the state, submitted that the earlier claim of 68% work done was wrong and no road was constructed so far and the new government has decided to re-tender the project.
The bench, also comprising Justices Arun Mishra and Adarsh Kumar Goel, expressed surprise on the statement by the SG who, during the last hearing on January 16, had said that 68% work was done.
"You have made a wonderful statement...We see today that nothing was being done. Where were your engineers," the bench asked. It, however, granted more time to the government but made it clear that there should be no further delay and asked it to come out with a calendar for completion of different stages.
Advocate A D N Rao, appearing for the court-appointed Environmental Pollution and Control Authority (EPCA), also questioned the delay, saying the timeline kept extending from 2005 to 2008 to 2012 to 2014 and now 2016.
http://timesofindia.indiatimes.com/followceleb.cms?alias=trucks,Supreme Court,Peripheral Expressway Highway,Haryana government,capital
Stay updated on the go with Times of India News App. Click here to download it for your device.
Anda sedang membaca artikel tentang
No work done on western e-way, Haryana tells SC
Dengan url
http://sehatputihgigiku.blogspot.com/2015/01/no-work-done-on-western-e-way-haryana.html
Anda boleh menyebar luaskannya atau mengcopy paste-nya
No work done on western e-way, Haryana tells SC
namun jangan lupa untuk meletakkan link
No work done on western e-way, Haryana tells SC
sebagai sumbernya
0 komentar:
Posting Komentar